The 110% Rule: What “Like-for-Like” Really Buys You in a Palisades Rebuild

Aug 26, 2026 | Land Use & Entitlements

The 110% Rule

Every rebuild in Pacific Palisades starts with the same quiet negotiation: how much of the old house can you keep, and how much of the new one do you actually want. The answer isn’t emotional. It’s a formula, and it lives inside two executive orders that now govern almost every parcel above Sunset and below the ridgeline.

Understanding that formula is the difference between a permit in weeks and a permit in months. Here is how the process actually works, where it breaks down, and where the opportunity still sits for developers, architects, and investors moving on Palisades lots.


What “Like-for-Like” Actually Means

Forget the phrase’s plain-English meaning for a second. In the City of Los Angeles’ post-fire framework, “like-for-like” is a technical envelope, not a design mandate. It’s defined by two executive orders, EO1 and EO8, and the one you fall under determines your review path, your timeline, and how much flexibility you keep on setbacks and non-conforming conditions.

EO1, the “Like-for-Like up to 110%” path, is the fast lane. Your new structure has to sit in substantially the same location and stay within 110% of the pre-fire footprint and height of the primary structure. Stay inside that line and you preserve legacy non-conforming features, like older setbacks that wouldn’t be allowed under current code, and you get the city’s fastest review track.

EO8, the “beyond like-for-like but zoning-compliant” path, is for owners who want more house. If your design exceeds 110% or changes the massing, you can still move through a streamlined process as long as the project complies with current zoning. EO8 removes Coastal Act and CEQA review for qualifying single-family projects in the Coastal Zone, which is a real advantage, but it costs you the non-conforming flexibilities EO1 protects.

The point worth sitting with: like-for-like isn’t about matching the old house’s aesthetic. It’s about matching its use, its location, and staying inside a footprint and height envelope. A owner can redesign almost everything about how a house looks and still qualify, as long as the geometry holds.


The Permit Sequence, Step by Step

For a single-family EO1 rebuild, the path generally runs in this order, though timelines shift with site conditions and whether self-certification or AI pre-check is used.

Debris clearance comes first, no exceptions. Phase 1 handles hazardous materials, Phase 2 handles general debris, and building permits will not issue until the lot is certified clean. Design and permit prep can start earlier, but occupancy of the pipeline depends on that clearance.

Documenting the pre-fire house is next, and it’s more consequential than it sounds. Prior plans, assessor records, photos, and insurance documentation all feed into the city’s determination of what existed before. In the absence of original plans, the city may lean on prior permits, Certificate of Occupancy records, coastal records, or aerial and LiDAR data to reconstruct the baseline.

EO1 eligibility gets confirmed against that baseline. Same location, no more than 110% of the prior footprint and height. Square footage alone isn’t the test. Basements and attached garages carry their own rules, and detached ADUs are treated separately, sometimes triggering bluff or biological review even when the primary structure sails through.

Surveys and geotech follow where needed. Lot line surveys are common since fences and markers were frequently destroyed. Hillside and geologically sensitive sites require geology and soils reports plus grading review, and these sites generally lose access to self-certification, which is the single biggest schedule risk on a hillside parcel.

Design still has to meet current code, even under like-for-like. Fire-resistant materials, ember-resistant vents, structural and Title 24 energy standards all apply regardless of which executive order governs the project. The citywide all-electric mandate has been repealed, so gas can be retained, but meaningful incentives now favor going all-electric anyway.

Submittal happens through LADBS ePlanLA or in person at the One-Stop Centers. Under EO1, complete applications get reviewed within 30 days, with permit clearances issued within 5 days of review completion, and many clearances have been eliminated outright for single-family rebuilds. What typically remains: BOE sewer and roof drainage, curb or driveway permits, lateral support permits where the right-of-way is affected, LAFD hydrant and access review, LADWP encroachment near easements, and Planning review only when coastal, canyon bluff, or biological resource triggers apply.

Permits issue, construction proceeds, generally with a 3-year validity window, and standard inspection checkpoints follow at foundation, framing, MEP rough-ins, insulation, and final.

Certificate of Occupancy closes the loop, once all finals including any fire, LID, or Planning conditions clear.

Two accelerants are worth building into any project plan from day one. The Self-Certification Pilot under EO6 lets qualified California-licensed architects self-certify code compliance on eligible rebuilds, bypassing LADBS plan check entirely, though other department reviews still apply and geologically sensitive sites are excluded. Separately, the AI Pre-Plan Check tool (Archistar/E-Check) offers a free preliminary compliance review for Palisades addresses. It doesn’t replace formal plan check, but it catches problems before they cost you a resubmittal cycle.


Where the Process Actually Breaks Down

The executive orders solved the paperwork problem. They didn’t solve the coordination problem, and that’s where most delays now live.

For developers and investors, the friction is financial before it’s regulatory. Insurance gaps are the recurring issue, with policies frequently falling short of what it costs to rebuild to current code, forcing owners into scope changes or fresh capital calls mid-project. Lot acquisition adds its own complexity, since many cleared parcels are now held by LLCs or institutional buyers, and packaging deals across multiple owners or trustees slows everything upstream of permitting. Utility coordination with LADWP, Public Works, and Sanitation can eat weeks, particularly where damaged infrastructure blurs the line between repair and upgrade. Layer on post-fire labor and material cost escalation, and some projects simply stall while owners weigh selling the lot instead of rebuilding.

For architects and designers, the hurdles are technical. Proving pre-fire conditions without original plans means reconstructing the building envelope from assessor records, photographs, or new surveys, and a small measurement error can knock a project out of EO1 eligibility entirely. Hillside and geotech triggers strip away self-certification and add geology and grading review to the timeline. Bluff and biological resource flags can pull Planning back into an otherwise routine rebuild, especially for detached ADUs or anything exceeding 110%. And meeting current seismic, fire-hardening, and energy codes inside a fixed footprint and height envelope forces genuinely creative structural and massing solutions.

For general contractors, it’s sequencing risk. Coordinating BOE, LAFD, and LADWP clearances alongside inspections can create stop-start cycles when comments arrive late. LADOT’s delivery windows, 9am to 3pm on weekdays and 8am to 6pm on Saturdays, constrain logistics, and any material storage in the right-of-way needs its own Building Materials Permit. Foundation decisions add another variable, since fire-damaged footings and slabs often can’t be reused, and the choice to demolish and re-pour reshapes both cost and schedule.

For homeowners and small builders, often acting as their own owner-builder, the pain points are more human. Understaffed city departments still create comment lag despite the executive orders. And scope creep is the quiet killer: once design starts, it’s common for owners to add square footage or height, which can silently move a project from EO1 into EO8 or standard review, adding months nobody budgeted for.


Where Activity Is Concentrated, and Where Room Still Exists

Rebuild activity has clustered heaviest in the core burn areas of the 90272 zip code, with investors and institutional buyers absorbing a significant share of cleared lots in the months following the fires.

The Village-adjacent grid and the “Alphabet Streets”, the flat, walkable blocks near Palisades Village, have become the most active pocket, favored for their location and simpler construction logistics. The ridgeline and hillside estates saw some of the most extensive destruction, and while many of these lots sit in geologically sensitive zones that slow permitting considerably, that hasn’t deterred investor purchases, it’s just changed the math on timeline.

Real opportunity still exists in the mid-canyon and bluff-edge parcels, where a substantial rebuild pipeline remains, though projects there should plan for bluff and biological review along with stricter access and hydrant analysis from the outset. The eastern Palisades and transition zones toward Brentwood show more mixed damage patterns, and while many parcels qualify cleanly for EO1 or EO8, they demand careful utility and right-of-way coordination that shouldn’t be treated as an afterthought.

Across all of these areas, the recurring drag factors are consistent: geotechnical and grading requirements, ambiguity around utility restoration scope, traffic and logistics constraints, and insurance or financing gaps that delay groundbreaking even after permits are already in hand.


The Incentive Layer Worth Building Into Your Pro Forma

Several city, utility, and state programs meaningfully reduce cost or time on a Palisades rebuild, and too many project budgets are built without accounting for them.

Permit fee suspensions under EO7 waive plan check and permit fees for eligible fire rebuilds, typically for owners of record as of the fire date, worth confirming current status at a One-Stop Center or on the LADBS Wildfire Rebuilding page. The expedited review timelines under EO1 and EO8 themselves function as a cost saving, given the 30-day review and 5-day clearance targets and the reduced clearance count for single-family projects.

The Pre-Approved Standard Plans Pilot offers a catalog of fire-resilient, pre-approved single-family and ADU designs with expedited permitting and suspended fees under EO7, a genuinely useful tool for investors looking to standardize across multiple lots. The Self-Certification Pilot under EO6 can shave real weeks off a schedule for qualified architects on eligible, non-hillside sites.

On the electrification side, a $22 million state incentive program launched in 2026 offers subsidies between $7,000 and $10,000 for all-electric rebuilds in disaster areas served by investor-owned utilities, with bonuses available for battery storage and passive home features. LADWP layers its own rebates on top for all-electric homes and appliances serving Palisades customers.

Beyond that, state funding for factory-built and modular housing, including a third funding round of $10 million, supports access to prefabricated homes designed to speed recovery while maintaining neighborhood character. And at the local level, officials have floated resilience district concepts using property tax mechanisms to fund fire-hardening upgrades like roofing, windows, and stucco, though progress here has been uneven and funding remains a real constraint.


Practical Guidance for Moving Faster

Lock EO1 eligibility early and hold the line on it. Staying within 110% footprint and height, in the same location, is worth defending against scope creep even when a client wants more house, because the moment a design drifts past that threshold, the entire review track changes.

Order survey and geotechnical work early if ZIMAS shows any hillside or bluff potential flagged as medium or high. That single check, done in week one instead of month three, is often the difference between an EO1 timeline and a standard review timeline.

Coordinate with LADWP and SoCalGas, along with hydrant and access review, during design rather than waiting for the permit stage. And use the One-Stop Centers on Sawtelle Boulevard and Marquez Avenue, where LADBS, Planning, LAFD, BOE, and LADWP staff coordinate in one place, to resolve cross-department questions in a single visit instead of five separate ones.


The Bottom Line

The regulatory architecture for Palisades rebuilds is genuinely favorable, faster review, fewer clearances, real fee relief, and a growing incentive stack for electrification and standardized design. But favorable rules don’t remove complexity, they just relocate it. The bottleneck has shifted from “can I get a permit” to “can I document my pre-fire baseline accurately, clear geotech on a hillside lot, and coordinate five departments without losing months to a comment cycle.”

That’s precisely the terrain where experienced land use guidance earns its keep, whether it’s confirming EO1 eligibility before a design is finalized, navigating a bluff or biological trigger on a canyon parcel, or sequencing utility coordination so it doesn’t stall a permit that’s otherwise ready to issue. For a deeper look at how these dynamics are playing out across both burn zones, see JDJ Consulting’s analysis of the Altadena and Palisades wildfire rebuild landscape.

If you’re evaluating a specific Palisades parcel, the fastest way to know your real timeline is to map its exact clearance path before design begins, flat lot versus hillside, bluff-flagged or not, self-certification eligible or not. That single exercise, done early, tends to save more time than any expediting program on the books.